NEC 2023 power calculator math for EV charger installers working in Utah.
Converting between kW and amps is the entry point for nearly every Utah EV install spec — manufacturers publish kW, but the panel, breaker, and feeder live in amps.
Worked example for Utah
A 150 kW EVSE draws roughly 625 A at 240 V single-phase, or 180 A at 480 V three-phase. Apply the NEC 2023 125% continuous-load multiplier before sizing the OCPD or feeder. Rocky Mountain Power typically meters DCFC sites at the 480 V three-phase service in Utah.
Code & Utilities
Utah currently enforces the NEC 2023 edition, adopted in 2024. That includes Article 625 (Electric Vehicle Power Transfer System) requirements: 125% continuous-load sizing on EVSE branch circuits, GFCI protection at outdoor receptacles, and provisions for energy management systems on shared circuits.
Utah's primary EV-relevant utilities are Rocky Mountain Power, Murray City Power, Logan Light & Power. Their make-ready, time-of-use, and demand-charge structures vary widely; pull the specific tariff before sizing service equipment.
Climate & Ampacity
Utah's representative summer design ambient is around 99°F, which yields a 0.82× ampacity correction factor at 75°C terminations per NEC 310.15(B)(1). Because the correction is below 0.9, conductors that "look fine" on a 30°C ampacity table will not carry their nameplate current here — always derate explicitly.
Utah takeaway
For three-phase math, always confirm the actual nameplate power factor — DCFC equipment is usually 0.95+ but older site-rated equipment can be lower, which changes the apparent power and the conductor pick.