Transformer Sizing Calculator for Georgia

NEC 2020 transformer sizing math for EV charger installers working in Georgia.

DCFC and large workplace EV deployments in Georgia typically need a dedicated 480 V three-phase service, which means sizing a pad-mount or dry-type transformer against the connected charger load plus the NEC 2020 continuous-load multiplier.

Worked example for Georgia

A 350 kW DC fast charger draws roughly 421 A at 480 V three-phase. Applying the 125% continuous-load factor (350 × 1.25 ≈ 438 kVA), then rounding up to the next standard transformer rating gives a 450 kVA minimum. Georgia's 94°F summer ambient does not directly derate the transformer, but it does push the secondary feeder ampacity down by 0.88× — so the secondary copper has to be sized accordingly.

Code & Utilities

Georgia currently enforces the NEC 2020 edition, adopted in 2021. That includes Article 625 (Electric Vehicle Power Transfer System) requirements: 125% continuous-load sizing on EVSE branch circuits, GFCI protection at outdoor receptacles, and provisions for energy management systems on shared circuits.

Georgia's primary EV-relevant utilities are Georgia Power, Oglethorpe Power, MEAG Power. Always verify the applicable tariff and any utility-specific requirements (CT cabinets, metering enclosures, demand limiters) at design time.

Climate & Ampacity

In Georgia, the 94°F summer ambient drives a 0.88× 75°C ampacity correction. Bake this into every Level 2 and DCFC conductor pick before you commit to a wire size. Because the correction is below 0.9, conductors that "look fine" on a 30°C ampacity table will not carry their nameplate current here — always derate explicitly.

Georgia takeaway

Coordinate primary-side voltage, impedance, and fault-current specs with Georgia Power early — interconnection lead times for new pad-mounts in Georgia can run 6-12 months on commercial DCFC sites.