Sizing an EV charger circuit in New York starts with NEC 2017 Article 625 — the EVSE branch must be sized to 125% of the continuous load. Hot-climate warm-band states like New York (88°F design ambient) also force a 0.88× ampacity correction at 75°C terminations.

Worked example for New York

For a 80 A Level 2 charger on a 240 V single-phase circuit, the OCPD is sized to 100 A (80 × 1.25 = 100.0 A, rounded up to the next standard breaker). The conductor must carry 100 A after New York's 0.88× correction — that typically lands at #6 AWG copper THWN-2 for a residential garage run, with conduit fill checked separately if you're stacking multiple home runs.

Code & Utilities

New York currently enforces the NEC 2017 edition, adopted in 2020. That includes Article 625 EVSE rules and the 125% continuous-load factor on charging branch circuits, though some 2020-cycle changes (like expanded EMS provisions) are not yet enforced statewide.

Major electric utilities serving New York include Con Edison, National Grid, PSEG Long Island, NYSEG, Central Hudson. Their make-ready, time-of-use, and demand-charge structures vary widely; pull the specific tariff before sizing service equipment.

Climate & Ampacity

New York's representative summer design ambient is around 88°F, which yields a 0.88× ampacity correction factor at 75°C terminations per NEC 310.15(B)(1). Because the correction is below 0.9, conductors that "look fine" on a 30°C ampacity table will not carry their nameplate current here — always derate explicitly.

New York takeaway

Always cross-check the EVSE manufacturer's listed maximum overcurrent rating; Con Edison may also have specific service-upgrade or load-management requirements you'll need to coordinate before final inspection.